Can we promise this date? What an agent answers in under a minute

The question sales asks most often is the one a planner can least often answer on the spot. A diagnosis agent returns four dated options — and names exactly whose orders would slip.

Nov 12, 20266 min readConvect AI

The question sales asks most often is the one a planner can least often answer on the spot. Answering it means checking the material, seeing which lines the order has to cross and when those lines are free, and working out who gets pushed if you force it in. That used to be a pass across several spreadsheets. Half an hour on a good day. The next morning on a bad one.

In a demo we handed the question to a planning-diagnosis agent. From the sentence to a dated answer: under a minute.

The plant in the demo coats and prints tinplate for food, beverage and paint cans. The customers, products and numbers below are demo data, not a customer measurement. If you want the multi-agent version of a rush order — which agent picks it up, which one finds the constraint, which one checks procurement — that walkthrough is here. This one is the question sales actually asks: can we commit?

The question

Sales forwards a request. The planner types one sentence:

Golden Grain Beverages wants 30,000 more sheets of the classic 4L print, for November 21. Can we make it?

The date is ten days out. The product needs two coating passes and then an eight-color press. Three operations.

Three steps, and only one of them is a conversation

Turn the names into IDs. “Golden Grain Beverages” resolves to customer C002. “Classic 4L” resolves to the product. A partial name is enough. The agent searches customers and products. If it can’t match, it says so and asks for another wording. It does not guess an ID and run the numbers anyway.

Trial the date. The optimization engine does this step. The agent’s job is to fill in the parameters. The engine checks the bill of materials, the specification and the rollers, to confirm the order could actually be released, then schedules it on a copy of the plan. The live plan doesn’t move.

Material is fine. The order needs 30,573 base sheets, and 341,056 are available. Ink and coating are covered. The specification is approved. The rollers are free.

Capacity isn’t. Every line this order would touch is between 89.6% and 93.3% loaded over the next two weeks. Dropped into the gaps in the current plan, 30,000 sheets will not finish this month.

Write the recommendation. The engine tried four approaches. The agent turns them into an answer, with the four options, and hands them to the planner.

Four ways to say yes, and what each one costs

OptionWhen 30,000 sheets finishThe price
A. Fit it into the current plan Not this month No other order moves
B. Jump the queue and replan everything November 14, on time 125 operations move. Four orders become newly late.
C. 20% overtime on three lines November 24, three days late Overtime cost. Nobody else’s date moves.
D. Split the order (recommended) 24,000 sheets on the 21st, 6,000 on the 25th Two lines at 20% overtime. No other order moves.

B looks like the best answer until you see whose dates it spends. The four orders belong to four other customers — a coatings company, a dairy, a biscuit maker, a seafood processor. That is buying one promise with four others. C touches nobody, and it is still three days late even with the overtime.

D is what the search found. If no existing order is allowed to slip, the most that can ship on the 21st is 24,000 sheets, and it needs 20% overtime on coating line 6 and print line 9. The remaining 6,000 finish on the 25th. Splitting has a second advantage: the two batches can run at the same time, on two lines. On another data set we compared, overtime on the whole order finished five days late. Split in two, it was one day late.

The agent’s first sentence is the conclusion. We cannot promise the full quantity on time. On the current plan it will not finish this month. Then where it’s stuck. Then what the four options actually do. Then the recommendation to split, with a note that the second date has to be confirmed with the customer.

Where the dates come from

None of them were estimated by a language model. The agent does three things: it understands the question, it calls the engine, and it explains the result. The schedule is computed by the optimization engine. Each of the four options is a full scheduling run.

Open the reasoning trace and every call is there — what was invoked, what was passed in, what number came back. Any figure in the answer can be found in that trace. That is the difference between an explanation and a fluent paragraph, and it’s why a planner can check the answer instead of trusting the tone. More on what has to be in that trace: an AI plan has to explain itself.

Submitting an option does not run it. The planner chooses “accept option D,” and only then does the system create the two orders, turn them into manufacturing orders, add the overtime and replan. If the customer doesn’t confirm, one click rolls it back.

Next to doing it by hand

By handThe agent
Material A stock sheet and a netting calculation The engine checks the bill of materials
Capacity A glance at the schedule for a gap A real schedule, on a copy of the plan
Who gets pushed Experience, and easy to miss Every order that would go late, and which customer owns it
The reply to sales “We’ll try.” “Let me get back to you.” Several options, each with a date and a cost
Time Half an hour to half a day About a minute

The last row is faster. The row that matters is the third. A rush order usually goes wrong in the order nobody noticed they had just delayed.

Two questions we get

What if the name is fuzzy? Usually that’s enough. Product names often include the customer, so “Golden Grain classic 4L” will resolve. If it can’t match, it says it can’t find it and asks you to rephrase. It will not invent an ID.

Can it reply to sales directly? We don’t recommend it. A date promise is a trade-off: overtime for one order, or a later date for another customer. The agent prices each path. The planner picks.

Want to run a promise-date question on your own orders? Book a demo, or see how planning agents are governed on the agents page.